Critical Project Management Tools
Part Two: Using Critical Project Management Tools
Answer the following questions about the project network below, using as much space as you need.
1. Map the earliest start times for each activity to the resource demands over time. What are the earliest start times for each activity?
2. Create a left-justified schedule for the project above.
3. Assuming you have five people available (with similar skills), level the schedule so it is consistent with resource availabilities. What is the new project duration?